Comprehensive operation and maintenance (O&M) services for the central heating facilities at the Oyu Tolgoi mine site.
The onsite team has delivered the O&M service since 2013, following initial pre-commissioning and commissioning support in 2011–2012.
The service covers the 130MW heating plant, the full heating distribution network, and underground buried water utility pipelines.
Central Heating Plant capacity.
Four 29MW units and two 7MW units.
Successfully maintained by the onsite team.
Continuous service delivery since 2013.
Operation and maintenance of the 130MW plant, utilizing four 29MW and two 7MW CFB boilers.
Management of the full heating distribution network.
Maintenance of all underground buried water utility pipelines.
Initial pre-commissioning and commissioning support was delivered in 2011–2012 before the ongoing O&M service.
Successfully maintaining 24/7 continuous operations.
Full-scope maintenance of all buried water pipelines, valves, and valve pits at the mine site.
Following initial pre-commissioning and commissioning support in 2011–2012, the onsite team has delivered over 14 years of uninterrupted O&M services without a major plant process stoppage.