ADR Process Plant Construction Project (2021-2022)

Client: Khan Altai Resource LLC by MAX GROUP
Location: Gobi Altai aimag, Yusunbulag soum
Role of participant: Contractor
Brief description of works:

  • Steel structure: 251 Ton)

  • Pipeline: 2.7km (HDPE, Carbon steel, PPH, PVC)

  • All plant equipment & Utilities

  • Instrumentation and automation

  • Commissioning & Testing including hand over

Key Features:

Turnkey project with complete construction and installation works of the plant and its equipment and systems.
 