Thermal Power Plant №3 Boiler Overhaul Maintenance Service Works (2005-2015)

Client: Thermal Power Plant #3
Location: Ulaanbaatar city
Role of participant: Contractor
Brief description of works:

  • Boiler overhaul service: 15 Sets

    • BKZ-220-100: 7 Sets

    • BKZ-75-39: 8 Sets

(Boiler waterwall tubes, Economizers, Air preheaters, Drums, Superheaters, Headers, Valves, Refractory liner, Insulation & Brickworks)

Boiler information:

  • Model- BKZ-220-100, High-pressure steam boiler, Steam flow rate - 220 t/h, Temperature – 540 ⁰C, Pressure -100 ata 

  • Model- BKZ-75-39, Medium-pressure steam boiler, Steam flow rate - 75 t/h, Temperature – 440 ⁰C, Pressure -39 ata 

Key Features:

  • High pressure, High temperature steam boiler

  • Boiler with pulverized coal fuel.